TP HSC Nursing project
• Site visit for first phase has been completed.
• Room 119 is completed. The phone may have to be relocated. Cabling looking into this.
• Update communication log, Blog, and timeline.
• Site walkthrough visit for review of locations in the first floor suite which is have minor renovations.
• Scheduled client move in. March 9th the WS and telephones will be stored until after spring break and March 19th the WS and telephones will be relocated to new suite locations on the first floor.
• Updated issues log.
• Update @Task and Blog
Next two weeks
• Follow up on room 119 for cabling of the phone.
• Update communication log, Blog, and timeline.
• Follow up with facilities PM on design of second phase of the project
• Transition project to Steve
• Update @Task and Blog
Health Sciences Center
| From HSC Renovation |
Thursday, March 1, 2012
Friday, January 13, 2012
Progress Update
EOC department moving from HSC to CAFRITZ on Dec 9th.
The cabling has been completed on 3rd floor 341
HSC nursing review with facilities
Coordinating work with facilities for a part of the project
Next two weeks
• Follow up on room 119 for cabling
• Update communication log, Blog, and timeline.
• Follow up with facilities PM on design of third phase o f the project
The cabling has been completed on 3rd floor 341
HSC nursing review with facilities
Coordinating work with facilities for a part of the project
Next two weeks
• Follow up on room 119 for cabling
• Update communication log, Blog, and timeline.
• Follow up with facilities PM on design of third phase o f the project
Wednesday, December 14, 2011
Progress Report
The project will in 3 phases
First Phase:specific scope of work and requisition for this winter's work only. That work includes:
Moving SIWS' from 321 and 322 to 325 and 326
Moving SIWS, projector and screen from 124 to 119
Installing infrastructure necessary to support new 347
Cabling will be done by college while coordinating work with facilities.
Phase two:
Design documents are still being reviewed and modified. Work expected during the spring semester:
First floor office area
321/322 practice lab
Phase three:
For work performed over summer:
Sim Suite
Minor modifications to third floor office suite
First Phase:specific scope of work and requisition for this winter's work only. That work includes:
Moving SIWS' from 321 and 322 to 325 and 326
Moving SIWS, projector and screen from 124 to 119
Installing infrastructure necessary to support new 347
Cabling will be done by college while coordinating work with facilities.
Phase two:
Design documents are still being reviewed and modified. Work expected during the spring semester:
First floor office area
321/322 practice lab
Phase three:
For work performed over summer:
Sim Suite
Minor modifications to third floor office suite
Monday, November 21, 2011
EOC department moving from HSC to CAFRITZ on Dec 9th.
The cabling has been completed
HSC nursing review with facilities
Coordinating work with facilities for a part of the project
Preparing cabling quote
Update communication log, Blog, and timeline.
Next two weeks
Follow up on EOC timeline and coordinate with IT groups.
Update communication log, Blog, and timeline.
Coordination meeting setup for Nov 30th.
The cabling has been completed
HSC nursing review with facilities
Coordinating work with facilities for a part of the project
Preparing cabling quote
Update communication log, Blog, and timeline.
Next two weeks
Follow up on EOC timeline and coordinate with IT groups.
Update communication log, Blog, and timeline.
Coordination meeting setup for Nov 30th.
Thursday, October 13, 2011
EOC department may be moving as a part this project. Timeline and number of users not determined as of today. Meeting with facilities and client preset for Oct 21st.
The relocation area for EOC is ready with data and voice.
Update communication log, Blog, and timeline.
Next two weeks
Follow up on EOC timeline and coordinate with IT groups.
Update communication log, Blog, and timeline.
Follow with facilities on any new timeline for the project.
The relocation area for EOC is ready with data and voice.
Update communication log, Blog, and timeline.
Next two weeks
Follow up on EOC timeline and coordinate with IT groups.
Update communication log, Blog, and timeline.
Follow with facilities on any new timeline for the project.
Tuesday, October 4, 2011
Progress Update
IT progress meeting on estimated timelines and equipment
Cabling quotes has been forward to facilities.
IT progress meeting Sept. 14 to review timelines and IT work to be done.
Update communication log, Blog, and timeline.
Next two weeks
Update communication log, Blog, and timeline.
Follow with facilities on any new timeline for the project.
Follow up on cabling walkthrough of rooms 344 and 345 for relocation of SIWS.
Cabling quotes has been forward to facilities.
IT progress meeting Sept. 14 to review timelines and IT work to be done.
Update communication log, Blog, and timeline.
Next two weeks
Update communication log, Blog, and timeline.
Follow with facilities on any new timeline for the project.
Follow up on cabling walkthrough of rooms 344 and 345 for relocation of SIWS.
Thursday, September 1, 2011
Progress Update
Schematic drawings have been done.
Facilities will be funding the 13 laptops and 1 WS.
Media resource campus manager is controlling the AV and SIM equipment.
Starting date is in the middle of November.
Cabling contractor is scheduled to be onsite for a walkthrough on Sept. 2 with college cabling group.
Facilities are working with the nursing (client) to try and start some work earlier then the middle of November. Possible start some work in September. No decision has of today. Sept 1st, 2011.
An E-mails has been sent to resource management for quotes on laptops and workstation
Follow up on cabling quote from vendor
Update communication log, Blog, and timeline.
Follow up on laptops and WS quotes.
Follow with facilities on any new timeline for the project.
Facilities will be funding the 13 laptops and 1 WS.
Media resource campus manager is controlling the AV and SIM equipment.
Starting date is in the middle of November.
Cabling contractor is scheduled to be onsite for a walkthrough on Sept. 2 with college cabling group.
Facilities are working with the nursing (client) to try and start some work earlier then the middle of November. Possible start some work in September. No decision has of today. Sept 1st, 2011.
An E-mails has been sent to resource management for quotes on laptops and workstation
Follow up on cabling quote from vendor
Update communication log, Blog, and timeline.
Follow up on laptops and WS quotes.
Follow with facilities on any new timeline for the project.