The project will in 3 phases
First Phase:specific scope of work and requisition for this winter's work only. That work includes:
Moving SIWS' from 321 and 322 to 325 and 326
Moving SIWS, projector and screen from 124 to 119
Installing infrastructure necessary to support new 347
Cabling will be done by college while coordinating work with facilities.
Phase two:
Design documents are still being reviewed and modified. Work expected during the spring semester:
First floor office area
321/322 practice lab
Phase three:
For work performed over summer:
Sim Suite
Minor modifications to third floor office suite
Health Sciences Center
| From HSC Renovation |
Wednesday, December 14, 2011
Monday, November 21, 2011
EOC department moving from HSC to CAFRITZ on Dec 9th.
The cabling has been completed
HSC nursing review with facilities
Coordinating work with facilities for a part of the project
Preparing cabling quote
Update communication log, Blog, and timeline.
Next two weeks
Follow up on EOC timeline and coordinate with IT groups.
Update communication log, Blog, and timeline.
Coordination meeting setup for Nov 30th.
The cabling has been completed
HSC nursing review with facilities
Coordinating work with facilities for a part of the project
Preparing cabling quote
Update communication log, Blog, and timeline.
Next two weeks
Follow up on EOC timeline and coordinate with IT groups.
Update communication log, Blog, and timeline.
Coordination meeting setup for Nov 30th.
Thursday, October 13, 2011
EOC department may be moving as a part this project. Timeline and number of users not determined as of today. Meeting with facilities and client preset for Oct 21st.
The relocation area for EOC is ready with data and voice.
Update communication log, Blog, and timeline.
Next two weeks
Follow up on EOC timeline and coordinate with IT groups.
Update communication log, Blog, and timeline.
Follow with facilities on any new timeline for the project.
The relocation area for EOC is ready with data and voice.
Update communication log, Blog, and timeline.
Next two weeks
Follow up on EOC timeline and coordinate with IT groups.
Update communication log, Blog, and timeline.
Follow with facilities on any new timeline for the project.
Tuesday, October 4, 2011
Progress Update
IT progress meeting on estimated timelines and equipment
Cabling quotes has been forward to facilities.
IT progress meeting Sept. 14 to review timelines and IT work to be done.
Update communication log, Blog, and timeline.
Next two weeks
Update communication log, Blog, and timeline.
Follow with facilities on any new timeline for the project.
Follow up on cabling walkthrough of rooms 344 and 345 for relocation of SIWS.
Cabling quotes has been forward to facilities.
IT progress meeting Sept. 14 to review timelines and IT work to be done.
Update communication log, Blog, and timeline.
Next two weeks
Update communication log, Blog, and timeline.
Follow with facilities on any new timeline for the project.
Follow up on cabling walkthrough of rooms 344 and 345 for relocation of SIWS.
Thursday, September 1, 2011
Progress Update
Schematic drawings have been done.
Facilities will be funding the 13 laptops and 1 WS.
Media resource campus manager is controlling the AV and SIM equipment.
Starting date is in the middle of November.
Cabling contractor is scheduled to be onsite for a walkthrough on Sept. 2 with college cabling group.
Facilities are working with the nursing (client) to try and start some work earlier then the middle of November. Possible start some work in September. No decision has of today. Sept 1st, 2011.
An E-mails has been sent to resource management for quotes on laptops and workstation
Follow up on cabling quote from vendor
Update communication log, Blog, and timeline.
Follow up on laptops and WS quotes.
Follow with facilities on any new timeline for the project.
Facilities will be funding the 13 laptops and 1 WS.
Media resource campus manager is controlling the AV and SIM equipment.
Starting date is in the middle of November.
Cabling contractor is scheduled to be onsite for a walkthrough on Sept. 2 with college cabling group.
Facilities are working with the nursing (client) to try and start some work earlier then the middle of November. Possible start some work in September. No decision has of today. Sept 1st, 2011.
An E-mails has been sent to resource management for quotes on laptops and workstation
Follow up on cabling quote from vendor
Update communication log, Blog, and timeline.
Follow up on laptops and WS quotes.
Follow with facilities on any new timeline for the project.
Tuesday, August 23, 2011
Progress Update
Discussed the client IT requirements and scheduled a meeting to review instructional software.
Reviewed the AV quotes and timelines.
Update communication log, Blog, and timeline.
Next two weeks
Follow up on cabling quote from vendor
Meeting scheduled for August 31st to review and discuss IT requirements with client and IT groups
Follow up with facilities on the comments for sequence work schedule.
Reviewed the AV quotes and timelines.
Update communication log, Blog, and timeline.
Next two weeks
Follow up on cabling quote from vendor
Meeting scheduled for August 31st to review and discuss IT requirements with client and IT groups
Follow up with facilities on the comments for sequence work schedule.
Friday, August 5, 2011
Progress Update
Requested cabling quote from vendor.
Quotes for SIWS relocation has been done by Media Resource group
Update communication log, Blog, and timeline.
Quotes for SIWS relocation has been done by Media Resource group
Update communication log, Blog, and timeline.
Tuesday, July 26, 2011
Progress Update
Reviewing the sequence work schedule from facilities.
Update communication log, Blog, and timeline.
Follow up with facilities on the comments for sequence work schedule.
Work on specifications and project plan
Update communication log, Blog, and timeline.
Follow up with facilities on the comments for sequence work schedule.
Work on specifications and project plan
Monday, July 11, 2011
Progress Update
Reviewing the sequence work schedule from facilities.
Follow up with facilities on the comments for sequence work schedule.
Update communication log, Blog, and timeline.
Follow up with facilities on the comments for sequence work schedule.
Update communication log, Blog, and timeline.
Thursday, June 23, 2011
Progress Update
Received a new set of drawing indicating room design.
Reviewed the design with a few questions.
The client and IT need to review the design of the rooms.
Follow up with client for telephone locations.
Client meeting scheduled for June 24 with facilities.
Reviewed the design with a few questions.
The client and IT need to review the design of the rooms.
Follow up with client for telephone locations.
Client meeting scheduled for June 24 with facilities.
Tuesday, June 14, 2011
Progress Update
A meeting is setup for June 9th with the client to review their IT requirements for each renovated location.
Reviewed the schematic drawings and estimated data drop location for each renovated area.
Prepared drawing with data drop locations.
Follow up with facilities on the schematic design.
Follow up with client for any additional information for other work to start prior to the actual construction timeline.
Reviewed the schematic drawings and estimated data drop location for each renovated area.
Prepared drawing with data drop locations.
Follow up with facilities on the schematic design.
Follow up with client for any additional information for other work to start prior to the actual construction timeline.
Friday, May 27, 2011
Project Activities
Attended On board schematic design meeting with client, facilities, and architects.
Setup a meeting with the client to review their IT requirements for each location for June 2nd.
Work on schematic design comments.
Follow up with NE on port availability.
Continue inquiring who is supposed to fund the cabling.
Setup a meeting with the client to review their IT requirements for each location for June 2nd.
Work on schematic design comments.
Follow up with NE on port availability.
Continue inquiring who is supposed to fund the cabling.
Saturday, May 21, 2011
Progress Update
Received the schematic drawings for review of the design.
Setup a meeting with client to review the schematic design and IT requirements.
OnBoard meeting setup for May 25 to review and discuss rooms designs.
Setup a meeting with client to review the schematic design and IT requirements.
OnBoard meeting setup for May 25 to review and discuss rooms designs.
Thursday, April 28, 2011
Progress Update
Working with client on additional work prior to actual project construction.
The schematic design is scheduled to be delivered the first week of May.
Follow up with facilities on the schematic design.
Follow up with client for any additional information for other work to start prior to the actual construction timeline.
The schematic design is scheduled to be delivered the first week of May.
Follow up with facilities on the schematic design.
Follow up with client for any additional information for other work to start prior to the actual construction timeline.