Attended On board schematic design meeting with client, facilities, and architects.
Setup a meeting with the client to review their IT requirements for each location for June 2nd.
Work on schematic design comments.
Follow up with NE on port availability.
Continue inquiring who is supposed to fund the cabling.
Health Sciences Center
| From HSC Renovation |
Friday, May 27, 2011
Saturday, May 21, 2011
Progress Update
Received the schematic drawings for review of the design.
Setup a meeting with client to review the schematic design and IT requirements.
OnBoard meeting setup for May 25 to review and discuss rooms designs.
Setup a meeting with client to review the schematic design and IT requirements.
OnBoard meeting setup for May 25 to review and discuss rooms designs.
Subscribe to: