Schematic drawings have been done.
Facilities will be funding the 13 laptops and 1 WS.
Media resource campus manager is controlling the AV and SIM equipment.
Starting date is in the middle of November.
Cabling contractor is scheduled to be onsite for a walkthrough on Sept. 2 with college cabling group.
Facilities are working with the nursing (client) to try and start some work earlier then the middle of November. Possible start some work in September. No decision has of today. Sept 1st, 2011.
An E-mails has been sent to resource management for quotes on laptops and workstation
Follow up on cabling quote from vendor
Update communication log, Blog, and timeline.
Follow up on laptops and WS quotes.
Follow with facilities on any new timeline for the project.
Health Sciences Center
| From HSC Renovation |
Thursday, September 1, 2011